 Post subject: maths
PostPosted: Fri Mar 09, 2012 8:27 am 
Offline

Joined: Wed Jan 11, 2012 8:36 pm
Posts: 18
Hi

Would anyone be kind enough to help with this maths question.

8 people take 10 hours to do a certain job, how long would it take 20 people to do the same job?

Thanks You


Top
 Profile  
 
 Post subject: Re: maths
PostPosted: Fri Mar 09, 2012 8:41 am 
Offline

Joined: Fri Oct 30, 2009 11:08 pm
Posts: 1225
Not sure, but:

If 8 people take 10 hours each that is 80 man hours in total ie 1 man would take 80 hours to do the job.

20 people should thus take 80 / 20 = 4 hours


I think!


Top
 Profile  
 
 Post subject: Re: maths
PostPosted: Fri Mar 09, 2012 9:42 am 
Offline

Joined: Wed Sep 23, 2009 2:09 pm
Posts: 178
Location: Great Notley
Minesatea wrote:
Not sure, but:

If 8 people take 10 hours each that is 80 man hours in total ie 1 man would take 80 hours to do the job.

20 people should thus take 80 / 20 = 4 hours


I think!



I make it 4 hours too.


Top
 Profile  
 
 Post subject: Re: maths
PostPosted: Fri Mar 09, 2012 2:43 pm 
Offline

Joined: Sat Nov 19, 2011 6:14 pm
Posts: 25
It is 4 hours.

You are basically increasing the number of people by a factor of 2.5. (8x2.5=20), therefore you would be decreasing the time taken by 2.5. So 10/2.5 = 4

Hope helps!


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 4 posts ] 

All times are UTC


Who is online

Users browsing this forum: Google [Bot] and 5 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
CALL 020 8204 5060
   
Privacy Policy | Refund Policy | Disclaimer | Copyright © 2004 – 2016